ARTIFACTORY: How to know the progress of the system import or estimate the finish time?
During the system import job, you may wonder when the system import job will finish.
Usually, you can monitor the migration process by looking at artifactory-import-export.log
As long as the artifactory-import-export.log is moving, it is a good sign.
Finally, you should see the following at the end of the system import process.
### Full system import finished ###
However, you want to know or estimate the finish time at the beginning or during the import process.
Currently, there is no progress bar for the system import job or to show the estimated completion time.
SolutionAs a workaround, you can run the following SQL query in DB
select count(*) from nodes where node_type=1;
You may estimate the current status by counting the current total artifact compared to the artifact count from the Source instance.